Performing basic & detail design and engineering for plants
Field
Power generation and chemical plant
Services
- Design of control loop
- Design of control logic
- Production of DCS I/O list
- Production of instrument list
- Production of valves list
- Production of instrument data sheet
- Production of instrument location drawing
- Design of air tubing layout
- Design of cable layout
- Design of instrument cable tray layout
- Design of instrument main cable layout
- Production of detail drawing of instrument installation
- Design of hook up drawing
- Design of interconnection wiring diagram
- Production of cable schedule
- Production of cable drum schedule
- 하드웨어 Integration
-
- Production of DCS I/O list
- Production of alarm set point list
- Production of SOE list
- Design of control loop
- Design of control logic
- 하드웨어 Integration
-
- Production of list of instruments
- Production of instrument data sheet
- Conducting of TBE
- 하드웨어 Integration
-
- Production of drawing of installation of instruments
- Production of drawing of laying out of cable
- Production of drawing of connection of cable
Order | Duration of project | Name of project | Performance | Clients |
---|---|---|---|---|
1 | 2018.08.17 ~ until now | S1 100MW Project | I&C Design | KDHEC |
2 | 2017.11.20 ~ until now | TAKHIATASH Project of Uzbekistan | I&C Design | HYUNDAI ENG |
3 | 2017.07.27 ~ until now | KALSELTENG-2 CFPP Project of Indonesia | I&C Design | HYUNDAI ENG |
4 | 2016.04.22 ~ until now | SBPL 500MW CFPP Project of Philippine | I&C Design | DAELIM |
5 | 2015.09.10 ~ until now | New Pyeongtaek CCPP Project | I&C Design | DAEWOO |
6 | 2015.07.06 ~ until now | KALSEL-1 CFPP Project of Indonesia | I&C Design | HYUNDAI ENG |
7 | 2017.10.23 ~ 2018.04.30 | ERUP Project (Prime G+ /LPG Merox) of Iran | I&C Design | DAELIM |
8 | 2015.07.15 ~ 2018.03.01 | Poseoung Biomass energy Project | I&C Design | DOHWA ENG |
9 | 2014.11.10~2017.04.08 | Mirfa 1,600MW IWPP Project | I&C Design | HYUNDAI ENG |
10 | 2014.03.18~2016.12.31 | Biskra/Jijel 1600MW CCPP Project of Algeria | I&C Design | HYUNDAI ENG |
11 | 2014.09.11~2016.09.30 | Pagbilao 420MW CFPP Project of Philippine | I&C Design | DAELIM |
12 | 2014.08.01~2016.06.30 | FFBL CPP CFBC Project | I&C Design | HHI |
13 | 2014.01.03~2016.06.30 | Rabigh2 IPP Project of Saudi | I&C Design | SAMSUNG C&T |
14 | 2013.10.08~2015.10.31 | CIPREL IV Add-on EPC Project | I&C Design | HDHC |
15 | 2013.09.12~2016.07.10 | Punta del Tigre CCPP Project | I&C Design | HYUNDAI ENG |
16 | 2013.04.17~2014.10.30 | SM200 Phase I Project of Philippine | I&C Design | DAELIM |
17 | 2013.04.08~2013.04.30 | TNB 1,000MW CFPP(IPP) Project of Malaysia | I&C Design | DAELIM |
18 | 2013.03.20~2014.03.20 | ShoaibaII CCPP Project of Saudi | I&C Design | DAELIM |
19 | 2012.11.23~2014.12.30 | Old Harbour CCPP Project of Jamaica | I&C Design | DAELIM |
20 | 2012.10.02~2014.12.30 | Thai Binh2 PP Project of Vietnam | I&C Design | DAELIM |
21 | 2012.07.03~2014.08.01 | EMAL PHASE II CCPP Project of Dubai | I&C Design | SAMSUNG C&T |
22 | 2012.03.01~2012.05.31 | 3-Step launch vehicle Project | I&C Design | HYUNDAI ROTEM |
23 | 2011.12.01~2012.02.03 | YANBU II HFO Thermal Power Project of Saudi | I&C Design | HANWHA E&C |
24 | 2011.11.01~2014.01.31 | UCH II CCPP Project of Bangladesh | I&C Design | HYUNDAI ENG |
25 | 2011.10.01~2014.11.30 | Pocheon CCPP Project | I&C Design | DAELIM |
26 | 2011.09.01~2013.08.30 | Sur IPP Project of Oman | I&C Design | DAEWOO E&C |
27 | 2010.06.01~2011.08.30 | PP11 Project of Saudi | I&C Design | HHI |